Milton Verizon Campus + South Deerfield: What the $26.25M Deal Actually Means

BBDN LOCAL INTELLIGENCE | MILTON + DEERFIELD

Milton Approved a $26.25M Deal for the Verizon Campus. Then It Froze New Development Around It.

Milton approved a purchase agreement for 51.32 acres at One, Two and Three Verizon Place and enacted a 30-day South Deerfield development moratorium at the same September 21 meeting. The acquisition has not closed, no final park plan is approved, and another public Council decision is still required before the City commits further.

Last verified: September 24, 2026

The headline is big enough by itself: Milton is under contract to buy the former Verizon campus in Deerfield for $26.25 million.

But the more important story is what happened around that deal.

At the same September 21 City Council meeting, Milton also enacted a temporary moratorium on certain new development applications across the South Deerfield study area and authorized an application for federal outdoor-recreation funding.

Put together, those actions show the City is not treating the Verizon property as an isolated land purchase. Milton is actively reconsidering how a major part of Deerfield should function, what land uses should be allowed, how public recreation fits into the district, and what development standards should govern the area next.

Where things stand right now

  • VERIZON PURCHASE AGREEMENT: Approved by Milton City Council
  • PROPERTY: One, Two and Three Verizon Place
  • SIZE: Approximately 51.32 acres
  • PURCHASE PRICE: $26.25 million
  • ACQUISITION CLOSED: No
  • DUE DILIGENCE: 60 days
  • INITIAL DEPOSIT: $100,000
  • ADDITIONAL DEPOSIT: $500,000, only after a later public Council decision if the City proceeds
  • SOUTH DEERFIELD MORATORIUM: Enacted for 30 days
  • FINAL PARK PLAN: Not approved
  • FEDERAL RECREATION GRANT: Application authorized, not awarded

What did Milton actually approve?

Milton City Council approved a purchase and sale agreement for the Verizon property covering approximately 51.32 acres at One, Two and Three Verizon Place.

The approved purchase price is $26.25 million. The agreement starts a 60-day due-diligence period and authorizes an initial $100,000 deposit.

That is not the same thing as closing on the property.

Before Milton waives its broad termination right or advances the additional $500,000 deposit, the City plans another public Council vote. If Milton continues with the transaction, closing is contemplated on or before December 1, subject to the agreement and due-diligence process.

The City can still walk away

This is the most important stage distinction.

  • The purchase agreement is approved.
  • The acquisition is not closed.
  • Due diligence is active.
  • The City still has a broad termination right during this period.
  • A later public Council vote is expected before Milton commits the next deposit.

So the correct description today is approved purchase agreement / due diligence, not “Milton bought the Verizon campus.”

Why this is bigger than one property

Milton already owns land directly across Deerfield Parkway from the Verizon campus.

The City acquired 21.37 acres at 300 Deerfield Parkway for $8 million in 2024, then added another 3.05 acres directly south for $750,000. Milton’s current Deerfield Active Park planning page lists the combined property at 24.42 acres.

If the Verizon transaction closes, those existing 24.42 acres plus the new 51.32-acre campus would give Milton approximately 75.74 acres of City-controlled Deerfield property.

The purchase prices alone would total approximately $35 million before demolition, site work, infrastructure, design, construction, financing or operating costs.

That is why the real question is not simply what happens to the old Verizon offices. The bigger question is what kind of district Milton is building around Deerfield Parkway, Windward Parkway, Highway 9 and the surrounding commercial area.

City of Milton Deerfield Active Area Park draft master plan for the existing 24.42-acre Deerfield Parkway park property
Separate project: City of Milton Deerfield Active Area Park draft master plan for the existing 24.42-acre park property along Deerfield Parkway. This is not a plan for the Verizon campus.

Then Milton paused new development applications

At the same September 21 meeting, Council enacted a 30-day temporary moratorium within the South Deerfield study area.

The resolution bars the acceptance of certain new zoning, land-use, site-plan and land-disturbance applications while the City conducts a focused review of the area’s:

  • Vision
  • Land uses
  • Development standards
  • Infrastructure
  • Implementation tools

The moratorium includes limited exceptions. City staff said pending applications were not affected.

This is not a permanent ban on development. It is a temporary pause on specified new applications while Milton reviews what it wants South Deerfield to become.

City of Milton Destination Deerfield subdistrict map showing North Deerfield, Central Deerfield, South Highway 9 and South Deerfield Parkway
South Deerfield in context. The City of Milton’s Destination Deerfield framework divides the larger district into four subdistricts. The September 21 moratorium applies specifically to the South Deerfield study area addressed by the City’s resolution.

What about the existing Verizon buildings?

City materials and current reporting indicate the existing office buildings are viewed as liabilities the City expects to remove if the transaction proceeds.

That still leaves major unanswered questions: demolition cost, environmental conditions, infrastructure needs, the final public-recreation program, and whether portions of the site could eventually support complementary commercial uses.

None of those pieces should be treated as final until the City completes due diligence and takes the next required public actions.

The federal grant could be large, but it is not secured

Council also authorized an application tied to the federal Outdoor Recreation Legacy Partnership program for South Deerfield.

Georgia’s 2026 ORLP program allows eligible applicants to request up to $15 million. The program requires at least a 1:1 match, meaning a full $15 million award would require at least $15 million in eligible matching resources.

Milton has authorization to apply. It has not been awarded $15 million.

The Georgia Department of Natural Resources says national selections are anticipated in May 2027.

What has NOT been approved

  • No completed Verizon property acquisition.
  • No final park master plan for the Verizon campus.
  • No construction contract for a new park district.
  • No confirmed demolition budget.
  • No final infrastructure package.
  • No approved commercial parcel sale.
  • No $15 million federal grant award.

Those distinctions matter because each would represent a different stage of the project.

Why Deerfield matters

Deerfield is one of Milton’s most important commercial areas. It sits around Highway 9, Windward Parkway, Deerfield Parkway, Webb Road and the GA 400 corridor, close to Alpharetta and some of North Fulton’s largest employment, retail and transportation assets.

Milton has already spent years building a Deerfield Implementation Plan, changing development standards and activating a Deerfield-focused Development Authority.

The Verizon acquisition, the new moratorium and the recreation-grant application bring those planning efforts into a much more tangible phase because the City itself could control a very large piece of the district.

What should residents watch next?

1. The due-diligence findings

The City is expected to examine the property, environmental conditions, demolition costs, legal issues and financial assumptions before deciding whether to proceed.

2. The second public Council decision

This is the clearest next decision point. Milton expects another public vote before giving up its broad termination right and advancing the additional $500,000 deposit.

3. What happens when the 30-day moratorium expires

The City could let the pause expire, modify its development rules, extend the moratorium, or take another action depending on what the focused South Deerfield review produces.

4. A real park and redevelopment concept

A land purchase is not a master plan. The next meaningful step will be a specific public concept showing recreation, roads, trails, infrastructure, potential commercial pieces and what happens to the existing buildings.

5. The federal grant outcome

If Milton’s ORLP application advances, that could materially affect how much of the project is paid locally. Until an award is actually made, it remains a funding opportunity rather than secured money.

Illustrative City of Milton Destination Deerfield rendering showing a walkable mixed-use streetscape vision
Illustrative vision only. This City of Milton Destination Deerfield rendering shows the broader design direction being considered for Deerfield. It is not an approved plan or rendering for the Verizon property.

Frequently asked questions

Did Milton buy the Verizon campus?

Not yet. Milton City Council approved the purchase agreement, but the City is still in due diligence and the transaction has not closed.

How much is Milton paying?

The approved purchase price is $26.25 million for approximately 51.32 acres at One, Two and Three Verizon Place.

What is the South Deerfield moratorium?

It is a 30-day pause on the acceptance of specified new zoning, land-use, site-plan and land-disturbance applications in the South Deerfield study area while Milton reviews the district’s vision, land uses, standards, infrastructure and implementation tools.

Does the moratorium stop every project?

No. The resolution includes limited exceptions, and City staff said pending applications were not affected.

Is a new park already approved?

No final park plan for the Verizon property has been approved. Milton already owns and is planning a separate 24.42-acre active-park property across Deerfield Parkway, but the Verizon site remains in the acquisition and due-diligence stage.

Did Milton receive a $15 million grant?

No. Council authorized an application. The ORLP program allows requests up to $15 million and requires matching resources, but an application is not a grant award.

What is the next major decision?

The most important near-term decision is whether Milton proceeds after due diligence. Another public Council vote is expected before the City advances the next deposit and waives its broad termination right.

Sources

Source note: BBDN distinguishes a purchase agreement from a completed acquisition, a grant application from an award, and planning from approved construction. This page will be updated when Milton completes due diligence, takes the next public vote, changes the South Deerfield moratorium, or advances a specific park and redevelopment plan.